Sunday, December 8, 2013

Demolition, Excavation, Footings & Forms

On Monday December 2nd, the fencing on the rear and side yard was relocated to separate the existing home from the new Coach House.  On Tuesday the demolition was started with the removal of the old storage shed and the willow stumps.  Excavation started Tuesday and finished Thursday morning.  Footings were prepared and poured on Friday morning.  On Saturday the footing forms were stripped and wall forms were erected, ready to pour the walls at 2:00 PM Monday.