Sunday, January 19, 2014

Taping, Utilities & Hardscape

The boarding was completed on Monday, cleanup was done on Tuesday morning and the tapers started on Tuesday afternoon.  This was a 4 day work week for the Hartley Homes crew however the good weather has helped with the progress. Excavation and preparation was done for all of the exterior concrete and paving stone areas.   We removed about 12-18 inches of soft soil then compacted and filled in with road base then topped the concrete areas with clear crush.  Pires Brothers placed and finished cement on Friday.  The tapers started on Tuesday afternoon, looking like another great job by EU-ROC Interiors Ltd.  Trenching for the power and water was also completed.  Fencing panels were picked up on Friday Morning and we installed the new fencing between the existing home and the new coach house.





Monday, January 13, 2014

Siding, Plumbing, Heating, Elecrical

Christmas has come and gone and construction continues at a steady pace, overall we lost 3 work days to the Holiday Season.  Exterior siding filled in most of the days surrounding Christmas.  Inspections for plumbing, heating, electrical, gas, framing and insulation were all completed between January 6th and January 10th.  Timber pergolas were also completed on Friday January 10th.  Drywall boarding started on the afternoon of the 10th and was completed on Monday January 13th.
Due to a manufacturing hiccup our cabinet supplier is unable to meet our target date of January 27th, cabinets will now be installed February 7th.