Sunday, December 15, 2013

Forming, groundworks, joists & walls

Forms were completed on Monday and the walls were poured.  On Tuesday the forms were stripped, foundation coating applied, weeping tile and rain water leaders were also completed.  Surveyors completed the top of wall survey and issued the survey certificate on Tuesday.  Sewer connections and inspections were completed and the site was back filled.  Due to the tight workspace, the rock drainage pit for the weeping tile was prepared during the back filling process, the trench is 25 ft long , 6 ft deep and 2 ft wide with 12 yards of 3-6" cobble at the bottom of the trench.  The joists were set and installed along with the and main floor sub floor and main floor exterior walls and most of the interior walls.  An impressive week considering the short days, cold weather and snow.